Developer fined for violating N.J. air law near AI data center. Residents say it’s a warning.

The owner of a massive campus in Kenilworth was fined $14,000 after a gas-powered generator on one of its buildings ran illegally for nearly a week last year, state records show. The building sits on the former Merck campus where CoreWeave is building a $1.8 b

Illustrative imageIllustrative image

The owner of a massive campus in Kenilworth was fined $14,000 after a gas-powered generator on one of its buildings ran illegally for nearly a week last year, state records show.

The building sits on the former Merck campus where CoreWeave is building a $1.8 billion artificial intelligence data center. But the generator is not part of CoreWeave's project.

The building is owned and operated by a group led by Onyx Equities, which owns most of the campus. CoreWeave owns a separate building there.

Still, some residents say the violation has added to their worries about the backup generators planned for CoreWeave's nearby data center. Generators that burn fuel release nitrogen oxides and other harmful pollutants when they run, environmental advocates have long warned.

"If a single malfunctioning gas generator can pollute our neighborhood unchecked for an entire week, residents have every reason to worry about 31 heavy-duty diesel generators operating on the exact same campus," said Madeleine Lee, a director with the Union County Residents Alliance Coalition, which circulated the state records this month. "A $14,000 state fine is barely a slap on the wrist for billion-dollar tech developments."

A CoreWeave spokesperson said their 31 generators are for emergency use, comply with state rules and are not currently running.

Onyx did not immediately respond to NJ.com's request for comment Monday.

The New Jersey Department of Environmental Protection found that the Onyx generator ran in violation of the state Air Pollution Control Act and the campus's air permit. The 180-kilowatt natural gas generator is only allowed to run during power outages, emergencies and routine testing.

The generator switched on Feb. 25, 2025, because of a faulty switch, according to letters Onyx sent to the DEP. Maintenance workers found it running during routine rounds on March 3 and shut it off that afternoon.

Onyx reported the problem to the DEP the next day. It replaced the faulty switch, added a backup alarm and began having workers check the generators in person several times per shift, the records show.

Onyx argued that it had properly maintained the generator and shouldn't be fined. The DEP rejected that argument and in December 2025 issued a $2,000 penalty for each of the seven calendar days the generator ran.

Adding to their worries, residents point to what happened in Vineland, where the DEP issued a $1.07 million penalty in September against DataOne, the developer of New Jersey's largest AI data center. The company installed and ran 62 natural gas generators without permits to power the site while it waited to switch to fuel cells.

Floodlight, a nonprofit newsroom that covers environmental issues, first reported on the generators. Using thermal drone footage, it documented at least 45 of them running in mid-August.

In Kenliworth, the former Merck headquarters spans more than 100 acres off Galloping Hill Road and includes about 2 million square feet of labs and offices. A group led by Onyx Equities, a Woodbridge-based developer, bought the property from Merck in 2023 for $187.5 million and has been marketing it to life sciences and technology companies as the Northeast Science and Technology Center, or NEST.

CoreWeave bought a separate lab building and about 27 surrounding acres for $322 million in August 2025. The company is converting the building into a 392,600-square-foot data center that is expected to be fully operational by early 2027. It could require up to 250 megawatts of power.

The Kenilworth Planning Board unanimously approved the project in May 2025. Opposition has grown since then, with residents rallying against the project each month at borough council meetings.